REIMANN builds outside sheet metal storage and optimizes hall occupancy

As part of a restructuring of production, we will install a new external sheet metal warehouse.
This will increase the storage capacity by 113to. The foundation work will start at the beginning of March. Completion will be around April/May 2021.We will also use this to move all processing machines (laser system, press brakes, rollers, hammer shears) to a separate hall.
This will shorten the distances between the individual operations/workplaces. The stainless steel area/stainless steel hall will also be moved to a larger hall. This measure will increase the area from 326m² to 670m².